6.1 Changeover Reduction: SMED
In high-mix electronics manufacturing, a common challenge to
The SMED Philosophy: Internal vs. External
Section titled “The SMED Philosophy: Internal vs. External”To support rapid changeovers, it is helpful to categorize and sequence tasks carefully.
- External Setup (OED): Activities performed while the machine is still running the previous product.
- Goal: The aim is to shift approximately 80% of preparation work to this phase.
- Examples: Mounting reels to offline feeder carts, removing
solder paste from refrigeration to warm up, retrieving stencils, verifying BOM data.
- Internal Setup (IED): Activities performed while the machine is stopped.
- Goal: This duration must be kept as brief as safely possible.
- Examples: Unclamping the stencil, swapping the feeder cart, adjusting conveyor width.
- The Principle: External tasks are ideally not performed while the machine is stopped. For instance, searching for a stencil key or a missing reel during downtime extends the internal setup unnecessarily.
External Preparation Methods
Section titled “External Preparation Methods”Effective preparation is usually completed and validated before the current run finishes.
- Feeder Kitting: Components are loaded onto Mobile Feeder Trolleys or Exchange Banks offline.
- Validation: Scanning and linking all reels to the feeder slot index using an offline docking station should be attempted. This helps eliminate the need to scan and verify during the active downtime window.
- Stencil & Paste:
- The next stencil should be retrieved and visually inspected for damage prior to changeover (often 30 minutes in advance).
Solder paste is removed from the refrigerator early enough (often 4 hours prior) to ensure it reaches ambient temperature naturally before the line stops.
- Conveyor Settings: The width of the next PCB is pre-measured. Manual conveyor spacers are set, or the digital width setting is recorded for quick entry.
Internal Execution (The “Pit Stop”)
Section titled “Internal Execution (The “Pit Stop”)”When the last board of the previous product exits the
- Printer Station:
- The used stencil and squeegees are removed promptly.
- The new stencil is loaded, and fresh, pre-stirred
solder paste is applied. - New support pins (magnetic or vacuum) are placed, often aided by a dedicated setup jig.
- Mounter Station:
- Bank Swapping: The entire feeder bank for the previous product is undocked, and the pre-loaded bank for the new product is docked in its place. Swapping individual feeders is typically avoided during this phase to save time.
- Support: Board support pins are adjusted to the defined coordinate map to help prevent PCB flex.
Reflow Oven :- The new thermal profile is loaded immediately. Modern
reflow ovens require time (often 5-15 minutes) to stabilize temperatures, making this the logical first step rather than the last.
- The new thermal profile is loaded immediately. Modern
Streamlining the Ramp-Up (First Article)
Section titled “Streamlining the Ramp-Up (First Article)”The changeover concludes when the first acceptable board is produced. The
- Electronic FAI: A dedicated
First Article Inspection (FAI) system (e.g., a scanner with golden sample overlay comparison) is often used instead of manual caliper or microscope checks. This helps keep FAI completion efficient, often under 3 minutes. - Setup Boards: A non-functional “Setup Board” can be run to verify
solder paste printing alignment and component placement polarity before committing live, valuable components. - Offline Corrections: It is best practice to correct program coordinates in the offline CAD data rather than “teaching” them directly on the machine during production. This ensures the master machine configuration remains consistent for future runs.
Final Checkout: Changeover reduction (SMED)
Section titled “Final Checkout: Changeover reduction (SMED)”| Metric / Action | Target / Standard Practice |
|---|---|
| Changeover Target | The aim is < 10 Minutes (Last Good Board to First Good Board) |
| External Prep | Must be completed before line stop |
| Feeder Strategy | Mobile Cart Exchange (single swaps must be minimized) |
| Validation | Offline Scanning must be performed |
| Oven Profile | Must be loaded first (to allow thermal stabilization) |
| Paste Condition | Ambient temperature naturally reached must be verified |
| Personnel | 2 Technicians should be considered (concurrent method) |
| Documentation | A Digital Checklist must be utilized |