Skip to content

3.1 APQP & PPAP

As is often said in engineering, quality cannot simply be inspected into a product at the end of the line; it really must be designed directly into the process. Advanced Product Quality Planning (APQP) is a structured framework of prevention. Its purpose is to ensure that the physical reality on the floor matches the original engineering intent before mass production ever begins. The Production Part Approval Process (PPAP) then provides the necessary, documented evidence that this APQP framework actually works at the required production rate. Skipping these critical planning steps usually leads to a stressful launch defined by line stops, heavy rework, and eventual field failures.

APQP is much more than a simple compliance checklist; it is a phased maturity model. It is best practice not to proceed to the next phase until the major risks of the current phase are thoughtfully mitigated.

The Logic of Phased Gates:

  • Phase 1 (Plan): The “Voice of the Customer” must be clearly defined.
    • If the core requirements are ambiguous, it is usually best to pause. A reliable, compliant product cannot be built against vague or shifting targets.
  • Phase 2 (Product Design): The underlying schematic and mechanical layouts must be frozen.
    • Output: The DFMEA (Design Failure Mode and Effects Analysis). This helps identify exactly what could break in the field.
    • Guideline: Critical Characteristics (CC) should be clearly identified here, such as a specific voltage rail tolerance or a critical heatsink gap.
  • Phase 3 (Process Design): The physical assembly line must be designed to appropriately handle the Product Design.
    • Output: The PFMEA (Process FMEA) and the Control Plan. These address how the build process itself might inadvertently fail the design (e.g. insufficient solder paste volume, or incorrect screw torque).
  • Phase 4 (Validation): The product must be built using the final, off-tool and off-process setup.
    • Action: The PVT (Production Validation Test) run must be executed. This is where the real-world data for process capability (Cₚ/Cₚₖ) and measurement system reliability (Gauge R&R) is collected.
  • Phase 5 (Launch): Mass Production (MP) is entered.
    • Requirement: An active Safe Launch Plan (Early Production Containment) must be kept running until all the initial exit criteria are confidently met.

Pro-Tip: When building documentation, DFMEA failure modes must not be copied directly over into the PFMEA. The DFMEA asks, “Will the capacitor overheat?” whereas the PFMEA asks, “Did the placement machine mount the wrong capacitor entirely?”

A PPAP is essentially a structured, data-driven agreement between the Supplier and the Customer. It officially states that the manufacturing process is capable of producing parts that meet all specifications, consistently, at the quoted production rate.

  • When introducing a New Part or a New Product, a Full PPAP is required.
  • When an Engineering Change Order (ECO) alters the design or the material, a Delta PPAP focusing only on the affected characteristics is usually sufficient.
  • When transferring or replacing critical Tooling, a Full PPAP is expected, because a new tool effectively creates a new process.
  • When a process has been completely stopped or dormant for >12 months, a Re-validation PPAP ensures the process has not drifted.

The specific expected submission level is defined right in the purchase order so expectations are clear from the start.

  • Level 1: Part Submission Warrant (PSW) only. (Common for low-risk or commercial off-the-shelf items).
  • Level 3: Full submission, complete with physical samples and all supporting data. (This is the standard default for most custom parts).
  • Level 5: Includes an on-site review of the process at the supplier’s facility. (Typically reserved for critical safety items).

While the full AIAG PPAP package typically contains 18 standard documents, the following elements are particularly critical to review:

  1. Part Submission Warrant (PSW): This is the cover sheet. Signing this document confirms accountability that the part is compliant and ready.
  2. Dimensional Results: Every single dimension called out on the drawing must be measured on a randomly selected sample of parts (usually 5 to 30 units).
    • Guideline: Global tolerance notes must be respected. The title block must be checked: if the drawing says “unless otherwise specified ±0.1mm,” every single un-dimensioned feature must be measured against that standard.
  3. Control Plan: This acts as the operational guide for the production floor. It maps every inspection step to a specific measurement tool and clearly defines the check frequency.
  4. MSA (Measurement System Analysis): This provides the statistical evidence that calipers, fixtures, and optical systems provide reliable, repeatable data.
    • If the Gauge R&R is greater than 30%, the measurement system likely needs improvement. It is best to fix the measurement fixture before time is spent investigating the manufactured part.

Pro-Tip: “Master Samples” (often called Golden Units) should be signed and dated. They must be kept stored in a controlled environment right at the Point of Use so inspectors have a reliable visual reference.

Control PointCritical RequirementGuiding Principle
Phased GatePhase N inputs must be fully complete before Phase N+1 begins.Granting “conditional passes” for safety-critical items must be avoided.
Drawing Compliance100% of the listed dimensions should be measured.An Out of Spec (OOS) reading generally results in a PPAP Reject.
Material CertsClear traceability back to the raw material lot/batch must be ensured.The material must match the approved manufacturer on the AVL.
CapabilityA Cₚₖ ≥ 1.33 for a stable, mature process is required.If the Cₚₖ < 1.33, continuous 100% inspection is typically required.
PSW SignatureShould be signed by the Quality Manager responsible for that line.Signing requires a thoughtful, prior review of the actual data.