3.1 Approved process materials list & specifications
While a standard
APML architecture & data attributes
Section titled “APML architecture & data attributes”The APML serves as the “Master BOM for the Process.” Every chemical consumable should be defined in the ERP system with the same rigor as electronic components.
Required data attributes
Section titled “Required data attributes”- Internal Material ID: Your internal part numbering scheme (e.g. CHE-0045).
Manufacturer Part Number : The specific vendor designation (e.g. Indium 8.9HF).- Functional Category: E.g.
Solder Paste , Tape, Flux, Adhesive, Cleaner. - Storage Profile: Required temperature or environmental conditions (e.g. Refrigerated 2°C to 8°C).
- Shelf Life: The established “Use By” window (e.g. 6 months from Date of Manufacture).
- Process Compatibility: Links to the specific manufacturing processes (e.g. a specific
reflow profile).
Sourcing & substitution logic
Section titled “Sourcing & substitution logic”Industrial chemicals can interact unexpectedly. A new cleaning agent might inadvertently damage a component’s
When Purchasing Requests a New Distributor:
- The Condition: The chemistry (Manufacturer and MPN) remains exactly the same, only the supplier changes.
- The Action: Conditionally Approved.
- The Verification: It must be ensured that the new distributor can maintain required handling conditions, such as “Cold Chain” transit logistics for temperature-sensitive materials.
When the Manufacturer Issues a PCN (
- The Action: The reformulated product must be treated as a new material.
- The Protocol: Process Engineering must evaluate and qualify the new formulation (e.g. via shear tests or Surface Insulation Resistance (SIR) testing) before it is released for production use.
When Considering an Alternate Brand:
- The Protocol: This must be treated as a full engineering change. “Generic” equivalents for critical materials like
solder paste rarely exist without process impacts. Substitution is only permissible if the alternate is already fully qualified and listed on the Approved Parts and Materials List (APML) as an approved alternate.
Storage & environmental controls
Section titled “Storage & environmental controls”Process chemistry is often perishable. The Warehouse team plays a vital role in maintaining shelf-life and environmental integrity to prevent materials from degrading into unusable waste.
Inbound cold chain (receiving protocol)
Section titled “Inbound cold chain (receiving protocol)”- The Risk:
Solder paste exposed to elevated temperatures can separate and perform poorly duringsolder paste printing. - The Protocol: The intake of temperature-sensitive shipments must be prioritized.
- The Verification: Any included temperature loggers or indicator dots must be inspected upon receipt.
- If a temperature excursion is indicated, the material must be quarantined and Procurement notified to arrange a return.
- The Execution: The material must be transferred to the appropriate cold storage promptly (e.g. within 15 to 30 minutes of receipt).
Shelf life & FIFO discipline
Section titled “Shelf life & FIFO discipline”- The Principle: First-In, First-Out (FIFO) inventory management must be consistently enforced.
- System Control: The ERP or
Warehouse Management System (WMS) should allocate the oldest active lot first and block the issuance of expired materials. - The Protocol: Expiration dates must never be manually extended without documented, formal authorization from Process Engineering or
Quality Assurance , based on requalification testing.
APML ownership & governance
Section titled “APML ownership & governance”The APML is a controlled technical document, not merely a procurement list.
Roles and Responsibilities:
- Process Engineering: Owns the technical specifications and has the authority to add or remove materials based on qualification data.
- Procurement: Manages supplier relationships, pricing, and fulfillment. Procurement executes purchases based directly on the approved parameters and AVL.
Quality Assurance : Periodically audits adherence to the APML, including checking expiration dates and storage logs.
Governance Cadence:
- Periodic reviews (e.g. annually) of the APML must be conducted to formally remove obsolete materials, update Safety Data Sheets (SDS), and verify compliance with regulations like RoHS or REACH.
The APML table structure
Section titled “The APML table structure”A structured APML must be implemented within the ERP or PLM system.
| Material ID | Category | Manufacturer | Mfr P/N | Approved Alt | Storage Temp | Shelf Life |
|---|---|---|---|---|---|---|
| SOL-001 | Indium | 8.9HF Type 4 | Alpha OM-338 | 0°C to 10°C | 6 Months | |
| FLX-002 | Rework Flux | Kester | 959T | None | Ambient | 2 Years |
| ADH-055 | Underfill | Loctite | 3513 | None | -40°C | 12 Months |
| CLN-101 | PCB Wash | Kyzen | Aquanox 4625 | Zestron FA+ | Ambient | 5 Years |
Final Checkout: Approved process materials list (APML) & specifications
Section titled “Final Checkout: Approved process materials list (APML) & specifications”| Control Point | Engineering Requirement | Target Goal |
|---|---|---|
| Complete Definition | All process chemicals are explicitly listed. | 100% Coverage in APML |
| Brand Substitution | Unauthorized substitutions are prevented. | Enforced |
| Cold Receiving | Temperature indicators checked upon receipt. | Standard procedure |
| Expiry Control | System prevents the use of expired lots. | Active within WMS/ERP |
| Material Lot tracked to production batches. | Maintained for critical materials | |
| Hard Ownership | Engineering approval required for APML changes. | Documented |