1.6 Sales → project handoff package
A signed PO carries little value until Operations can definitively execute it. The Sales to Project Management (Project Manager) handoff serves as a formal Quality Gate. The Sales cycle extends beyond the signature, officially concluding only when the Project Manager formally accepts the “Baseline Scope.” Until validation occurs, the project liability remains with the Sales organization.
The handoff gate: logic & rules
Section titled “The handoff gate: logic & rules”Handoff implies a binary state: the project is “Owned by Sales” or “Owned by Project Manager”, with no transitional gray area.
- The Acceptance Rule:
- Incomplete Data Packs (e.g. missing
Gerbers or pricing details) necessitate a formal rejection by the Project Manager. Sales retains absolute ownership until the package achieves completeness. - Ambiguity within the project scope requires an immediate rejection of the handoff.
- Logic: Project Manager accountability for a production schedule requires fully defined and comprehensive inputs; managing to undefined variables is not a sustainable practice.
- Incomplete Data Packs (e.g. missing
The baseline scope package
Section titled “The baseline scope package”The following artifacts must be transferred to establish the “Project Truth.”
Commercial baseline
Section titled “Commercial baseline”- The Quote (Unredacted): The Project Manager requires full visibility into the calculated margins and the “Assumptions Register” (Chapter 1.3).
- Why: Unawareness of pricing exclusions (such as omitting “Custom Packaging” from the baseline cost) can lead the Project Manager to inadvertently provide unpaid services, eroding the project margin.
- The Contract (MSA/PO): Highlight non-standard terms (e.g. “Liquidated Damages for late delivery”).
Technical baseline
Section titled “Technical baseline”- Golden Data Pack: The validated ZIP file (BOM,
Gerbers , XY) from Chapter 1.2. - Deviation List: Any engineering deviations agreed to during the pre-sales phase (e.g. “Customer accepted Blue Solder Mask instead of Black”).
Strategic context
Section titled “Strategic context”- Stakeholder Map: Who is the “Decision Maker” vs. the “Influencer”?
- Example: “Talk to Bob for technical queries, but only Alice can approve cost increases.”
- The “Why”: Why did the customer buy? (Speed? Quality? Price?). Align the project KPIs to this driver.
Pro-Tip: Explicitly document any “Shadow Promises.” Any informal commitments made by Sales (e.g. suggesting a highly expedited, unverified delivery date) must be communicated immediately so the Project Manager can proactively manage the customer’s expectations.
The kickoff agenda
Section titled “The kickoff agenda”The alignment process must be standardized. A “strategy session” should be held instead of a “meet and greet.”
Phase 1: internal kickoff (sales + Project Manager + engineering)
Section titled “Phase 1: internal kickoff (sales + Project Manager + engineering)”- Goal: Sanity check the deal before facing the client.
- Agenda:
- Review Margin & Cost constraints (Can we afford air freight?).
- Review Technical Risks (Is the BGA pitch too tight?).
- Define the “United Front” (What is the official lead time message?).
Phase 2: external kickoff (team + customer)
Section titled “Phase 2: external kickoff (team + customer)”- Goal: Establish authority and communication channels.
- Agenda:
- Introductions: Formally transfer “Point of Contact” from Sales to Project Manager.
- Scope Re-Verification: “We are building Rev A, Qty 1000. Correct?”
- Risk Review: “We see a risk with Component X. Here is our mitigation plan.”
- Cadence: “We will report status every Tuesday at 10:00 AM.”
RAID seed (initial log)
Section titled “RAID seed (initial log)”The RAID log (Risks, Assumptions, Issues, Decisions) is the Project Manager’s navigation chart. Sales must “seed” the first entries based on the negotiation phase.
Risks (future uncertainty)
Section titled “Risks (future uncertainty)”- Entry: “Component U1 is single-source. Allocation risk high.”
- Mitigation: “Pre-buy stock immediately.”
Assumptions (accepted as true)
Section titled “Assumptions (accepted as true)”- Entry: “Customer commits to providing the programming fixture by [Date].”
- Impact: Delays in fixture delivery cause a proportional, day-for-day slip in the overall production schedule.
Issues (current problems)
Section titled “Issues (current problems)”- Entry: “Credit limit insufficient for full material buy.”
- Action: Finance to approve temporary increase.
Decisions (agreed facts)
Section titled “Decisions (agreed facts)”- Entry: “Approved use of alternate Resistor brand Y.”
Handoff completeness checklist
Section titled “Handoff completeness checklist”| Item | Description | Status |
|---|---|---|
| Signed Contract | PO / MSA with all signatures. | [ ] |
| Golden Data Pack | Version controlled ZIP (BOM, Gerber, etc.). | [ ] |
| Quote Model | Including margin breakdown & assumptions. | [ ] |
| Contact List | Customer Tech/Commercial/Logistics contacts. | [ ] |
| RAID Seed | Initial risks and known constraints logged. | [ ] |
Initial RAID template
Section titled “Initial RAID template”| ID | Type | Description | Impact | Owner | Status |
|---|---|---|---|---|---|
| R-01 | Risk | Lead time for CPU is 52 weeks. | Line down | Purchasing | Open |
| A-01 | Assumption | Customer will pay NRE before | Cash flow | Sales | Verified |
| D-01 | Decision | Ship partial quantity (50%) allowed. | Revenue | Project Manager | Closed |
Final Checkout: Sales → project handoff package
Section titled “Final Checkout: Sales → project handoff package”| Check Item | Validation Criteria | Criticality |
|---|---|---|
| Project Manager Acceptance | Project Manager has explicitly signed off/accepted the package. | BLOCKER |
| Scope Clarity | Quantity, Revision, and Specifications are locked. | BLOCKER |
| Margin Visibility | Project Manager knows the target cost and profit margin. | High |
| Hidden Risks | ”Shadow Promises” and verbal agreements documented. | High |
| Communication | ”Official Channel” established (Sales steps back). | Medium |
| Kickoff Date | Scheduled within 48 hours of Purchase Order (PO) receipt. | Medium |