3.2 PVT / pilot run readiness: tooling, test & yield
PVT (
A strict “Stop” policy is enforced: Pilot runs must not commence unless the line is fully production-ready.
Readiness definition (the entry criteria)
Section titled “Readiness definition (the entry criteria)”A
Tooling & fixtures
Section titled “Tooling & fixtures”- Hard
Tooling : Molds must be T1 or T2 status with texture approved. No softtooling allowed. - Assembly Fixtures: All jigs (screw guides, press-fits, glue alignment) must be final design. No 3D printed temporary jigs.
- Stencils: Nano-coated stainless steel stencils cut to DFM-optimized apertures.
Test readiness
Section titled “Test readiness”Testing must be binary. Subjectivity is the enemy of scale.
FCT (Functional Test ): Automated sequence required. No manual probing.- Limits Locked: Pass/Fail thresholds (Voltage, Current, dB, Lux) are frozen in software.
- MSA (Measurement System Analysis):
Gage R&R must be < 10%. High tester variance makes it impossible to accurately measure product variance.
The golden sample
Section titled “The golden sample”- Definition: A physical unit that represents the “Perfect Standard” for cosmetic and subjective fit/finish.
- Requirement: One Golden Sample must be present at the Final Quality Control (FQC) station.
- Sign-off: Signed/dated by the Customer and Quality Manager.
Pro-Tip: The Engineering team must be removed from the assembly line during PVT. An operator’s inability to assemble the unit using only the Standard Operating Procedures (SOP) indicates a process failure. Engineers must observe, not touch.
Yield targets & rework limits
Section titled “Yield targets & rework limits”PVT must expose weaknesses. Issues must not be masked by allowing infinite rework.
Yield targets:
Section titled “Yield targets:”- FPY (
First Pass Yield ): Target ≥ 95%. - Line Yield (After Rework): Target ≥ 98%.
- Cₚₖ (Process Capability Index): ≥ 1.33 for critical dimensions.
The “touch limit”
Section titled “The “touch limit””Defects found during PVT must trigger an immediate process review.
- A single failure mode occurring more than three times consecutively necessitates a line stop and an immediate Engineering investigation.
- Units requiring more than two rework attempts must be scrapped, as they no longer represent a standard product and will skew reliability data.
Pilot readiness checklist
Section titled “Pilot readiness checklist”These checkpoints must be verified 48 hours before the scheduled pilot start.
| Category | Checkpoint | Required State |
|---|---|---|
| Documentation | Work Instructions (SOP) | Printed, laminated, and posted at every station in local language. |
| Control Plan | Inspection points (IQC, IPQC, OQC) defined with sampling rate (AQL). | |
| Material | Clear to Build (CTB) | 100% material on-site. No “shortages to be hand-carried.” |
| Component Preparation | Moisture Sensitive Devices ( | |
| Process | Profile measured and within spec for specific | |
| Torque Settings | Electric drivers calibrated to spec; Bit verification done. | |
| Test | Test Stations | 100% operational; “Red Rabbits” (known bad units) successfully failed. |
The pilot report template (the approval artifact)
Section titled “The pilot report template (the approval artifact)”The Pilot Report is the “Gate Key” to Mass Production. It summarizes the build data into a commercial decision.
Section a: executive summary
Section titled “Section a: executive summary”- Build Quantity: [Input]
- Start/End Date: [Input]
- Result: [PASS / CONDITIONAL PASS / FAIL]
Section b: performance matrix
Section titled “Section b: performance matrix”| Metric | Target | Actual | Delta | Status |
|---|---|---|---|---|
| FPY (Yield) | ≥ 95% | 96.2% | +1.2% | PASS |
| Cycle Time | 60 sec | 68 sec | +8 sec | FAIL |
| Shortages | 0 | 0 | 0 | PASS |
| Critical Defects | 0 | 1 | +1 | FAIL |
Section c: top 3 pareto (failure modes)
Section titled “Section c: top 3 pareto (failure modes)”- Ref Designator U14: Solder Bridge (Quantity: 5). Root Cause: Stencil aperture too wide.
- LCD Connector: Bent Pin (Quantity: 3). Root Cause: Operator handling error.
- Cosmetic: Scratch on case (Quantity: 2). Root Cause: Fixture interference.
Section d: open issues list (OIL)
Section titled “Section d: open issues list (OIL)”- Issue: Cycle time 8 seconds over target.
- Action: Add second screwing station to balance line.
- Owner: Ops Manager.
- Due Date: Prior to Mass Production.
Section e: sign-off
Section titled “Section e: sign-off”- Approvals: [Plant Manager Signature] | [Quality Manager Signature] | [Customer Operations Signature]
Final Checkout: NPI / pilot run readiness: tooling, test & yield
Section titled “Final Checkout: NPI / pilot run readiness: tooling, test & yield”| Control Point | Passing Criteria | State |
|---|---|---|
| Red Rabbits | Test stations successfully caught known bad units. | Pass / Fail |
| Cycle Time | Line speed matches the quoted commercial cost model. | Yes / No |
| Cosmetic Alignment | Boundary samples (Marginal Pass/Fail) defined for FAI. | Defined |
| Software Version | Firmware checksum matches the Golden Release. | Matched |
| Serial numbers recorded and linked to test data in database. | Active |