    2.3 Shortage management: the “chase” process

    A material shortage is an operational challenge that directly impacts factory utilization and revenue recognition. Shortage management requires a structured, proactive “War Room” approach: daily intervention and cross-functional coordination until the Clear-to-Build (CTB) signal is restored and verified.

    A shortage exists when the Committed Supply is less than the Firm Demand within the active production window. It must be managed formally as a defined operational issue, rather than informally via email.

    The Shortage Review should ideally occur daily at a fixed time. Focus the meeting on active resolution rather than passive status reporting.

    • Duration: It must be kept concise (e.g. 15-30 minutes maximum).
    • Focus: Blocker removal and exception management.
    • Actionable Data: For every critical shortage line, the owner should provide:
      1. The Constraint: Specific Part Number and Quantity.
      2. The Impact: The projected Line Stop Date.
      3. The Next Action: The specific tactical step being taken to resolve it.
      4. The Deadline: When a definitive update is expected.

    Mitigation options (the execution playbook)

    Section titled “Mitigation options (the execution playbook)”

    When the standard supply channel encounters delays, Procurement must explore parallel recovery paths simultaneously.

    When the Standard Channel is Delayed:

    1. Spot Buy / Independent Sourcing:
      • Vetted independent distributors must be engaged. Strict adherence to counterfeit testing protocols (e.g., AS5553/AS6081) must be ensured when buying on the open market.
      • The Financial Decision: It must be evaluated if the premium cost of a spot buy is offset by preventing a more expensive factory line-down event.
    2. Alternate Sourcing (Engineering Pivot):
      • The Action: Engineering must be asked to review for a potential “Drop-in Replacement.”
      • The Logic: Generic commercial equivalents (e.g., standard logic gates or passive components) should be checked where components from different manufacturers are functionally identical.
    3. Logistics Acceleration:
      • The Action: Freight must be upgraded to expedited methods (e.g., Next Flight Out or Air Freight).
      • The Evaluation: Financial responsibility must be determined based on whether the supplier missed their commitment or if internal demand spiked inside standard lead time.
    4. Production Re-sequencing:
      • The Action: Splitting the build lot to produce a partial quantity with available stock should be evaluated, allowing the SMT line to run while awaiting the balance.
      • The Caution: This increases setup costs and tracing complexity, so it is typically a last resort.

    Escalation is the structured application of corporate leverage. Organizational tiers must be utilized to resolve road-blocks efficiently.

    Escalation TierTrigger PointTypical OwnerTactical Action
    Level 1Shortage Initially IdentifiedBuyerValidate PO status, request expedite, check franchised distributor stock.
    Level 2Vendor unresponsive > 24 hrsSr. BuyerEngage Supplier Sales Manager to request allocation release.
    Level 3Impact arriving < 1 WeekSCM DirectorEscalate to Vendor Leadership; potentially authorize broker premium.
    Level 4Line Down ImminentExecutiveExecutive-to-Executive communication; deploy critical resources.

    The “Chase” must be managed through a highly visible, centralized dashboard (e.g., a Kanban board or shared tracker tool).

    CriticalityImpact DateMPNQty ShortRoot CauseMitigation PlanOwnerNext Update
    CRITICALOct 24MCU-F405500Vendor Fab Delay1. Evaluating spot buy. 2. Engineering reviewing ‘RGT6’ alternative.J. Doe14:00
    HighOct 28Conn-USB2kDemand SpikeAir Freight booked (Awaiting tracking number).S. SmithOct 26
    MedNov 05Res-10k10kYield IssuePulling in quantity from the subsequent PO line.J. DoeOct 30

    Resolving the immediate crisis is essential, but structurally addressing the underlying flaw prevents recurrence.

    A shortage incident should ideally include identifying the root cause and implementing a corrective action within the ERP or planning system.

    Examples of Structural Fixes:

    • Issue: Consistent Vendor OTD FailureFix: Adjust Vendor Scorecard and evaluate increasing the system Safety Stock buffer temporarily.
    • Issue: Inaccurate ERP Lead TimeFix: Update the ERP Lead Time parameter (e.g. from 12 weeks to 20 weeks) to reflect market reality.
    • Issue: Unforecasted Demand SpikeFix: Review the sales forecasting process or formalize buffer inventory agreements with the customer.
    • Issue: Significant Incoming Quality RejectsFix: Issue a Supplier Corrective Action Request (SCAR).

    Recap: Shortage Management Escalation and Mitigation

    Section titled “Recap: Shortage Management Escalation and Mitigation”
    ParameterRequirementActionOwnerCondition
    Shortage DeclarationCommitted Supply < Firm Demand within active production window.Initiate formal daily War Room stand-up (15-30 min). Focus on blocker removal.Cross-functional teamUntil Clear-to-Build (CTB) is restored and verified.
    Daily Stand-up DataFor each critical shortage line.Owner must provide: 1. Constraint (MPN & Qty), 2. Impact (Line Stop Date), 3. Next Action, 4. Update Deadline.Line OwnerDaily, until resolution.
    Mitigation ExecutionStandard supply channel is delayed.Execute parallel paths: 1. Spot Buy (with counterfeit testing), 2. Engineering review for drop-in replacement, 3. Upgrade freight, 4. Evaluate production re-sequencing.Procurement / EngineeringBefore line stop date.
    Escalation TriggerLevel 1: Shortage identified. Level 2: Vendor unresponsive >24 hrs. Level 3: Impact <1 week. Level 4: Line down imminent.Escalate per tier: L1: Buyer validates PO. L2: Sr. Buyer engages Supplier Sales Manager. L3: SCM Director escalates to vendor leadership. L4: Executive communication.Per escalation tier (Buyer → Executive)Immediately upon trigger.
    Root Cause ClosureShortage incident resolved.Identify root cause and implement structural fix (e.g., update ERP lead time, issue SCAR, adjust safety stock).Process OwnerPost-resolution, to prevent recurrence.