    2.2 Quarterly business review

    A Quarterly Business Review (QBR) is not merely a social check-in or a grievance session focused on a single late shipment. It is a critical, strategic calibration event. Its primary purpose is to synchronize the customer’s 12-month demand roadmap with the factory’s technical capabilities and capacity planning. Without a disciplined QBR process, the commercial relationship often degrades into transactional chaos, forcing teams to react to shortages rather than proactively preventing them.

    Presenting data without clear context must be avoided. Every slide in the presentation must drive toward a specific decision or a corrective action.

    Metrics achieving Green (On Target) status provide an opportunity to strategically propose cost optimizations or volume increases.

    Metrics indicating Red (Off Target) status require a clear presentation of the Root Cause Analysis (RCA) alongside the established recovery timeline.

    The meeting agenda should uniformly follow this hierarchy:

    1. Performance (Look Back): Cold, hard data reviewing the last 90 days.
    2. Continuous Improvement (The Fix): The current status of CAPAs (Corrective Actions) and ongoing engineering initiatives.
    3. Roadmap (Look Forward): Forecast reconciliation and the NPI (New Product Introduction) pipeline.

    Subjective assessments (e.g. “We feel quality has improved”) are generally insufficient. Use the following objective metrics to define the health of the manufacturing system.

    Metric CategoriesKey Performance Indicator (KPI)Target / Definition
    QualityFPY (First Pass Yield)% of units passing test on the first attempt (Target: >98%).
    DPPMDefective Parts Per Million at the customer line.
    RMA TurnaroundAverage days from receipt to repair/credit (Target: <10 days).
    DeliveryOTIFOn-Time In-Full. % of lines shipped by the committed date.
    Commit Rate% of requested dates accepted without a push-out.
    CommercialForecast Accuracy(Actual Orders / Forecasted Demand) for the period.
    E&O LiabilityValue of Excess & Obsolete material aging > 90 days.

    Standardizing the presentation format helps ensure efficiency and consistency across all accounts.

    • High-level health check (Red/Yellow/Green status).
    • Top 3 achievements of the quarter.
    • Top 3 critical risks (e.g. Component EOL, Tariff changes).
    • Visual representation of the KPI table above.
    • Trend lines are essential. A single number provides limited value; the trend (improving vs. degrading) indicates process stability.

    Slide 3: quality deep dive (Pareto analysis)

    Section titled “Slide 3: quality deep dive (Pareto analysis)”
    • Yields dropping below the formally agreed target necessitate a Pareto chart highlighting the top three failure modes.
    • Clearly display the specific engineering fix addressing the #1 failure mode.
    • Present lead time trends for critical commodities (Silicon, PCBs, Connectors).
    • Action: Any components requiring immediate “Bridge Buys” to cover identified lead time gaps must be highlighted.
    • Input: The Customer provides their forecast for Q+1, Q+2, and Q+3.
    • Output: The Factory confirms its capacity allocation.
    • The E&O liability status must be reviewed. Written authorization to either scrap the material or ship it to the customer must be requested.

    Discussions often fade, but written registers endure. The QBR process is incomplete without a formalized, signed Action Register. This serves as the control document for the subsequent 90 days.

    • ID: A unique identifier for tracking (e.g. Q3-01).
    • Issue: A clear technical description of the problem (e.g. “Solder bridging observed on U45”).
    • Action: The specific, concrete task to be executed (e.g. “Modify the stencil aperture design”).
    • Owner: The name of one specific individual responsible for the task (either at the Customer or the Supplier).
    • Due Date: A fixed target date. Vague entries like “TBD” are not acceptable.
    • Open: The action is defined, but work has not started.
    • In Process: Engineering or remediation work is currently active.
    • Validation: The solution has been implemented, and the team is monitoring the results.
    • Closed: Effectiveness has been verified by objective data.

    A healthy partnership requires bidirectional accountability. It must be ensured the QBR concludes by formally ratifying the “Give/Get” commitments.

    • Implementing the specific Corrective and Preventive Actions (CAPA) outlined for the top quality issue.
    • Reserving necessary manufacturing line capacity for the agreed Q4 forecast volume.
    • Holding strategic buffer stock for agreed-upon critical components.
    • Providing firm Purchase Order coverage for long lead-time components (Risk Buys).
    • Dispositioning Excess and Obsolete (E&O) material (deciding to Pay or Scrap) within 30 days of notice.
    • Freezing the production schedule for the upcoming 4 weeks (No pull-ins or push-outs allowed during this window).

    ParameterRequirementAction / AnalysisOwnerStatus
    FPY (First Pass Yield)>98%Pareto analysis for top failure mode; present engineering fix.Quality EngineerRed if below target.
    OTIF (On-Time In-Full)100%Cross-reference with customer Forecast Accuracy.Planning ManagerRed if off target.
    Forecast AccuracyActual vs. Forecast (deviations analyzed)Basis for capacity allocation; review for planning failures.Customer / PlanningAlways included.
    RMA Turnaround Time<10 days averageRoot Cause Analysis for delays.Service EngineerRed if off target.
    Action Register ItemFixed due date (no “TBD”)Track via register (ID, Issue, Action, Owner, Due Date).Designated IndividualOpen, In Process, Validation, Closed.
    E&O LiabilityDisposition within 30 days of noticeRequest written authorization to scrap or ship.CustomerReviewed in QBR.
    Critical Component Lead TimeMonitor trendsHighlight components requiring immediate “Bridge Buys”.Supply ChainAction required for gaps.