2.4 Control Plan + Reaction Plan (Stop/Contain/Release Rules)
The Control Plan (CP) is the operational constitution of the manufacturing floor. While the PFMEA predicts theoretical risk, the Control Plan prescribes the actual policing of that risk. It is the single source of truth that translates engineering intent (GD&T, Specs) into operator reality (Gauges, Checks, Reaction).
The Reality Check: If a process step or inspection is not in the Control Plan, it does not officially exist. An operator performing an "informal check" is uncontrolled variance.
The Golden Thread: Lineage of Logic
A Control Plan does not appear in a vacuum. It is the final link in the data chain. You must demonstrate direct traceability.traceability:
- DFMEA (Design Risk) defines Key Product Characteristics (KPCs).
- Example: "Shaft Diameter" is critical for bearing fit.
- PFMEA (Process Risk) defines Key Process Characteristics (KCCs).
- Example: "Machine Spindle Speed" controls the Shaft Diameter.
- Control Plan defines How we check the KCC to protect the KPC.
- Action: Measure Spindle Speed every hour; Measure Shaft Diameter every 5 parts.
The Rule: Every High RPN (Risk Priority Number) in the PFMEA must have a corresponding detection or prevention line item in the Control Plan. No orphans.
The Three Phases of Control
The Control Plan evolves as process maturity increases. Do not copy-paste the Production Plan into the Prototype phase.
1. Prototype Control Plan
Objective:Validation of Design.Method:100% inspection, typically manual data logging.Focus:Dimensional verification and material testing.
2. Pre-Launch (Safe Launch) Plan
Objective:Validation of Process Stability (Early Production Containment).Method:Increased frequency (e.g., 200% of normal sampling).Focus:Catching "Infant Mortality" issues and debugging the line.Exit Criteria:Defined number of defect-free runs (e.g., 3000 units or 3 shifts).
3. Production Control Plan
Objective:Statistical Control.Method:Sampling based on Capability (Cpk).Focus:Monitoring process drift.
Anatomy of a Control Line Item
AAmbiguity validin the Control Plan entry requires five specific definitions. Ambiguity here causes operator error. Each entry must define five specific parameters.
1. Characteristics (What)
Distinguish between Product (The Output) and Process (The Input).
- Bad: "Check Solder."
- Good: "Solder Paste Height (Process)" and "Fillet Wetting Angle (Product)."
2. Specification / Tolerance (The Standard)
Must match the print exactly.
- If the print says 10.0 ± 0.1
mm,mm -> Then the CP lists 9.9 – 10.1 mm. - Pro-Tip: Do not use "Visual OK" as a spec. Use "No burrs visible at 4x magnification" or reference a specific Limit Sample ID.
3. Evaluation Technique (The Tool)
Define the Measurement System.
- Hardware: Caliper, CMM, Go/No-Go Fixture (Quote the specific Gauge ID).
Software:Vision System, ICT.Requirement:Validation: The Gauge listed must have avalidpassing Gage R&R (MSA) study.
4. Sample Size & Frequency (The Rhythm)
ThisFrequency is a function of Process Capability (Cpk), andnot Risk."standard practice."
- If Cpk < 1.33 (Unstable) -> Then 100% Inspection.
- If Cpk > 1.67 (Capable) -> Then Sample 1 piece every 4 hours.
- If Safety Critical -> Then Mistake Proofing (Poka-Yoke) or 100% Auto-Check required.
5. Reaction Plan (The Consequence)
This is the most critical and often neglected column. It tells the operator exactly what to do when the check fails.
- Bad: "Notify Supervisor." (
Too vague,Vague, slow). - Good: "Stop Line. Segregate last 2 hours of production. Adjust Tool Offset +0.02mm. Re-measure."
DynamicThe ManagementReaction Plan: The "OCAP"
The Reaction Plan is the Out of Control Action Plan. It is not a suggestion; it is an algorithm for the operator.
The "Stop-Call-Wait" Syndrome:
Do not write "Call Quality Engineer" as the primary reaction. The line will stop for hours waiting for you. The Reaction Plan must empower the operator to Contain and Correct autonomously where possible.
Reaction Logic Levels:
- Level 1 (
LivingOperator):Document)Re-measure to confirm. If confirmed fail -> Stop Machine -> Tag Part "Reject". - Level 2 (Setter/Lead): Adjust process parameters (within Control Plan limits). Change tool. Re-verify first piece.
- Level 3 (Escalation): If Level 2 fails to fix the issue -> Call Engineering. Initiate Non-Conformance Report (NCR).
Stop / Contain / Release Rules
You must define the strict criteria for stopping the line and, more importantly, the criteria for restarting it.
1. Stop Rules (When to Halt)
- Safety Breach: Any failure of a safety curtain, interlock, or E-stop. Immediate Hard Stop.
- Consecutive Rejects: Three (3) consecutive parts failing the same parameter.
- Setup Verification Fail: First Article Inspection (FAI) failure.
- Trend Violation (SPC): Seven points on one side of the mean (Shift) or points outside Control Limits.
2. Containment Rules (The "Bucket" Protocol)
When a defect is found, you must assume all parts produced since the last "Good" check are suspect.
- Traceback: Identify the time of the last successful inspection.
- Quarantine: Isolate 100% of WIP (Work in Progress) produced between "Last Good Check" and "Now."
- Screening: You must inspect every single unit in the suspect window for the specific defect.
- Clean Point: Establish a "Clean Point" (Serial Number or Time Stamp) where known good production resumes.
3. Release Rules (Restart Criteria)
You cannot just turn the machine back on. The process is "Guilty until proven Innocent."
- Correction Verified: The root cause (broken tool, wrong setting) must be physically corrected.
- Setup Verification: Run a new First Piece. It must measure nominal (centered in spec), not just "in spec."
- Sign-Off: For Safety or Critical Characteristic failures, the Quality Manager or Process Engineer must physically sign the "Restart Authorization."
The Three Phases of Control
The Control Plan isevolves notas aprocess staticmaturity artifact. It drives the feedback loop.increases.
Prototype Control Plan:
Scenario: Customer Complaint (Field Failure)Action:Method:Review100%theInspection.CP.ManualWasdatathe defect characteristic listed?If Yes:The method/freq was insufficient. Update CP to tighten inspection.logging.If No:Goal:The CP was incomplete. AddValidate thecharacteristicdesignimmediately.intent.
Pre-Launch (Safe Launch) Plan:
- Method: Increased Frequency (e.g., 200% of normal sampling).
Scenario:Goal:ProcessContainChange"Infant(ECO)Mortality" issues. Exit criteria = 3000 defect-free units.
Production Control Plan:
Action:Method:IfStatisticaltheSamplingtool,basedmaterial,onorCpk.- Goal:
machineMonitorchanges,processthe CP must be re-revised and re-approved before production resumes.drift.
Final Checklist
Control Point | Critical Requirement |
|
Traceability | High RPN |
|
Spec Alignment | Control Plan | |
Reaction Plan |
| Must |
|
| Last Good Check |
|
| Critical Failure |
| Safe Launch | New |
|
|
|