9.4 Internal MRB & Quarantine Discipline
The Material Review Board (MRB) process is not a "repair shop" or a storage room for mistakes; it is a crime scene investigation. Every item in the MRB cage represents a failure of the process controls upstream. As a Quality Director, your mandate is simple: Segregation must be absolute. If a non-conforming part can be physically mistaken for a good part and re-introduced to the line, your Quality System has already failed. MRB is the "Air Gap" between a production anomaly and a customer escape.
Physical Segregation (The Red Cage)
Quarantine is not a status in the ERP system; it is a physical reality. Electronic blocking is insufficient because operators do not read SAP screens when grabbing a reel from a cart.
The "Red Cage" Standard:
- Physical Barrier: The Quarantine area must be a locked cage or a distinct room with controlled access.
- Visual Logic: All MRB material must be tagged with a RED "Non-Conforming" label immediately upon detection.
- Inventory Gap:
- IF material is physically in the cage:
- THEN it must be electronically transferred to the "MRB" or "Blocked" storage location in ERP.
- Risk: If the physical and digital states drift, Planning will schedule production against bad inventory, causing line-down events.
The MRB Hierarchy (Disposition Logic)
The MRB is a decision-making body, not a committee for debate. The Quality Manager holds the casting vote. Use the following logic to disposition material efficiently:
- Disposition: Return to Vendor (RTV)
- Trigger: Supplier defect confirmed.
- Action: Issue SCAR + Debit Memo. Move to Shipping Dock within 48 hours.
- Disposition: Scrap
- Trigger: Product cannot be recovered economically or safely.
- Action: Mutilate before disposal. Do not just throw PCBs in a dumpster; they will be harvested for components on the gray market.
- Disposition: Rework
- Trigger: Recoverable process defect (e.g., missing screw, cold solder).
- Requirement: A documented Rework Instruction (WI) must be approved by Engineering before touching the unit. "Fix it" is not an instruction.
- Disposition: Use As Is (UAI)
- Trigger: Cosmetic defect or minor deviation that affects form but not fit/function.
- Requirement: Mandatory Engineering Deviation signed by the Design Authority. Quality cannot approve UAI alone.
MRB Aging & Velocity
The most common failure mode of an MRB system is the "Graveyard Effect"—parts enter and never leave. This hides WIP costs and obscures yield data.
The 30-Day Hard Stop:
- IF a discrepancy remains open > 30 days:
- THEN it defaults to SCRAP.
- Logic: If Engineering or the Supplier hasn't cared enough to resolve it in a month, the material is effectively dead. Stop paying to store it.
- Metric: Measure "Average Days in MRB." Target < 7 Days.
Scrap Security (Grey Market Protection)
High-value silicon and sub-assemblies are targets for theft. Scrapped material must be treated as "Hazardous Waste" in terms of chain of custody.
- Protocol: High-value scrap (CPU, Memory, Completed PCBAs) must be witnessed destroyed.
- Certificate of Destruction (CoD): Required for all proprietary or branded material.
Final Checklist
Control Element | Requirement | Critical Rule |
Access Control | Physical Lock | Quality Personnel Only (Key/Badge access) |
Identification | Tagging | Red Tag attached immediately upon failure |
UAI Decision | Deviation | Engineering Signature Required (No verbal approvals) |
Aging Limit | Velocity | > 30 Days = Automatic Scrap |
Rework | Documentation | Approved WI Required before work begins |
Disposal | Security | Mutilate/Crush to prevent resale |