1.6 Purchase Order (PO) Management
A Purchase Order (PO) is not an administrative suggestion; it is a legally binding contract that defines the specific configuration, schedule, and quality standard for a transaction. If the PO is vague, the liability for failure sits with the buyer, not the supplier. A "perfect" PO eliminates ambiguity regarding what is being bought, when it must arrive, and how it must be verified.
The PO as a Contract: Required Fields
Every PO issued must contain a specific dataset to be considered valid. Missing data creates "escape points" for suppliers to deliver non-conforming material.
Identification & Revision Control
- PO Number: Unique identifier.
- Revision: Must increment with any change (e.g., Rev A -> Rev B).
- Date: Issue date triggers the validity window of the quote.
Line Item Definition
- MPN (Manufacturer Part Number): The exact alphanumeric string (e.g.,
STM32F405RGT6). Do not rely on internal Part Numbers alone. - Description: Brief technical text (e.g., "MCU 32-bit ARM Cortex-M4").
- Quantity: Explicit unit count.
- Unit Price: Agreed contract price (referenced to Quote #).
Commercial & Logistics
- Incoterms: Standardized delivery term (e.g., "FCA Hong Kong").
- Payment Terms: Net 30 / Net 60.
- Ship-To: Exact warehouse address and attention party.
- Promise Date: The "Dock Date" required by planning.
Quality Clauses (The Fine Print)
- Traceability: "Vendor warrants goods are new, original, and traceable to OCM."
- Date Code: "Date Codes must be within 24 months of receipt unless waiver approved."
- Substitutions: "No functional equivalents or substitutions allowed without prior written approval."
Approval Thresholds
Risk scales with value and complexity. Implement a tiered approval matrix to prevent unauthorized liability.
Value Threshold ($) | Risk Category | Approver Required |
< $5,000 | Low (Class C) | Buyer |
$5k – $50k | Med (Production) | Sr. Buyer / Commodity Mgr |
$50k – $250k | High (Strategic) | Supply Chain Director |
> $250k | Critical (CapEx) | VP Operations / CFO |
Any Value | NCNR / Custom | + Engineering Manager |
The ACK Discipline (Acknowledgement)
Sending a PO is only half the transaction. The contract is not valid until the supplier confirms acceptance.
The "24/48" Rule:
- Action: Supplier must ACK receipt within 24 hours.
- Action: Supplier must Confirm Schedule (Commit Date) within 48 hours.
Valid vs. Invalid ACK:
- Valid: "We accept PO #123. Line 1 confirmed for delivery 2023-10-15."
- Invalid: "Received thanks." (This confirms receipt of email, not acceptance of terms).
- Conflict: If Supplier ACK Date ≠ PO Need Date, this is a Rejection. It triggers immediate negotiation. You must either update the ERP with the new date or expedite.
Pro-Tip: If a supplier fails to ACK within 48 hours, assume the order is lost. Do not wait for the due date to find out.
Change Control & Substitutions
Changes happen. Uncontrolled changes cause line-down events.
Scenario 1: Supplier Requests Date Push
- Protocol: Calculate impact on production build.
- If Line Down Risk: Escalate to Global Supply Manager for allocation fighting.
- If Safe: Update ERP "Commit Date" field. Do not overwrite original "Need Date" (you need to track the variance for vendor scoring).
Scenario 2: Supplier Offers Substitution
- Protocol: STOP.
- A buyer cannot approve technical subs.
- Route request to Engineering via Deviation Request form.
- If approved, Revise PO to new MPN. Never receive Part B against a PO for Part A.
Scenario 3: Partial Shipments
- Protocol: Allowed only if defined on the PO ("Partials Allowed").
- Constraint: Final balance must be delivered before the invoice is paid in full (depending on terms).
PO Quality Audit Checklist
Before hitting "Send," scan the PO for these common failure modes.
Check | Failure Mode | Fix |
UoM Check | Ordering "100" meaning "100 Reels" vs "100 units" | Verify Unit of Measure |
Price Check | Variance from Quote or Standard Cost | Re-validate Quote |
Rev Control | Sending Rev A PDF when system is at Rev B | Sync PDF to System |
Spec Check | Missing specific color/finish on custom parts | Add Note/Drawing Ref |
Address | Shipping to HQ instead of Factory | Verify Ship-To Code |
Final Checklist
Control Point | Requirement | Critical Threshold |
Contract Completeness | All mandatory fields populated | 100% |
ACK Status | Confirmed Commit Date in ERP | < 48 Hours from Issue |
Revision Match | PO Rev matches BOM Rev | Critical |
NCNR Flag | Signed agreement attached | If Terms = NCNR |
Date Code Limit | < 24 Months specified | Printed on PO |
Approval Chain | Sign-off limits respected | Automated Workflow |