1.2 Supplier Selection & The AVL

The Approved Vendor List (AVL) functions as the primary firewall for the manufacturing ecosystem. Permitting unvetted entities to inject material into the supply chain guarantees downstream failure, whether through counterfeit components, sudden insolvency, or unmanaged lead time variability. A rigid, data-driven AVL acts as a hard gate within the ERP, physically preventing the generation of Purchase Orders to unauthorized sources.

Qualification Criteria

Entry to the AVL requires objective evidence of stability and security. Subjective relationships do not mitigate risk.

Authorization & Traceability

  • Requirement: Vendor must hold valid Franchise Agreements or Authorized Line Cards for the specific commodities being sourced.
  • Verification: Validate directly with the Component Manufacturer (OCM).
  • Why: Direct authorization ensures an unbroken Chain of Custody (CoC), nullifying counterfeit risk.

Quality Management System (QMS)

  • Requirement: Active ISO 9001 certification (minimum); AS9100 or IATF 16949 (preferred for automotive/aerospace).
  • Verification: Validate certificate scope and expiration date via the issuing registrar.
  • Why: A certified QMS proves the supplier possesses documented processes for handling non-conformances (RMA) and corrective actions (SCAR).

Financial & Operational Solvency

  • Requirement: 3 years of audited financials or D&B rating > 3.
  • Why: Prevents "ghosting" during critical shortages or warranty claims.

Commercial Terms

  • Requirement: Alignment with standard payment terms (Net 30/60) and Incoterms (Ex Works / FCA).
  • NCNR Constraint: Non-Cancellable Non-Returnable (NCNR) terms are restricted to Custom (MG-04) or End-of-Life (EOL) buys.

AVL Lifecycle Workflow

Manage the vendor lifecycle through distinct states. The ERP system must enforce these states logically.

Phase 1: Request & Evaluation

  • Input: Sourcing Request Form submitted by Commodity Manager.
  • Action: Quality Assurance performs desk audit (certs, financials) and optional site audit.
  • Decision:
    • Pass: Move to Provisional.
    • Fail: Move to Blacklisted.

Phase 2: Provisional (Probation)

  • Condition: Limited to 3 POs or $50k spend cap.
  • Action: 100% incoming inspection on all receipts.
  • Transition: If 3 lots pass acceptance → Move to Approved.

Phase 3: Maintenance & Performance

  • Routine: Quarterly review of On-Time Delivery (OTD) and Quality Acceptance Rate (QAR).
  • Logic:
    • If OTD < 85% for 2 consecutive quarters → Downgrade to Conditional.
    • If Critical Counterfeit/Fraud incident → Immediate Disqualified.

The AVL Entry Record

Standardize the data structure for every AVL entry to ensure database integrity.

Field

Description

Data Type

Owner

Vendor ID

Unique ERP identifier (e.g., V-00432)

Alphanumeric

Finance

Vendor Name

Legal Entity Name

String

Sourcing

Classification

OCM / Franchised Disty / Broker / Service

Enum

Sourcing

Status

Approved / Provisional / Conditional / DNU

Enum

Quality

Commodity Scope

Allowed Purchase Groups (e.g., MG-02 only)

Array

Sourcing

Risk Rating

Composite score (1-5) based on financials/geo

Integer

Risk Mgmt

QMS Expiry

Date of ISO certificate expiration

Date

Quality

Exception Logic: One-Time & Spot Buys

Operational reality sometimes necessitates deviating from the standard AVL (e.g., Line-Down situations). Enforce strict protocols for these exceptions.

Scenario: Shortage Waiver (Broker/Independent)

  • Trigger: Authorized channels cannot meet commit date; production stoppage imminent.
  • Protocol:
    1. Authorization: CTO or VP Supply Chain signature required.
    2. Vendor Type: Create temporary vendor record defined as "One-Time Vendor".
    3. Validation: Mandatory 3rd-party test report (AS6081) linked to the specific lot.
    4. Closure: Vendor record automatically deactivates after PO receipt.

Scenario: NPI / Engineering Sample

  • Trigger: Component required for prototype; not yet carried by volume distributors.
  • Protocol:
    1. Limit: Maximum spend < $1,000.
    2. Restriction: Parts Forbidden for Mass Production BOMs.
    3. Flag: Item Master marked as "Eng-Only".

Final Checklist

Control Point

Requirement

Critical Threshold

ERP Lockout

Non-AVL PO Generation

Blocked

Ownership

Master Data Management

Supply Chain / Quality

Review Cycle

Vendor Performance Review

Quarterly (QBR)

Doc Retention

ISO/AS9100 Certs

Current (Non-Expired)

Broker Access

Independent Distributor usage

Exception Only

Traceability

Chain of Custody Evidence

100% of Transactions