3.1 NPI Stage Gates (Commercial + Technical)
New Product Introduction (NPI) is the highest-risk phase in the manufacturing lifecycle. It is where margins are engineered or destroyed. A failed NPI phase results in "unstable equilibrium"—a product that can be built, but never profitably or predictably. We use a strict Stage-Gate process to enforce discipline. We do not "drift" into production; we pass specific gates with binary (Pass/Fail) criteria.
The Gate Logic
The process is divided into 4 standard phases: EVT, DVT, PVT, and SOP.
Rule: You cannot enter the next stage until the Exit Criteria of the current stage are signed off. "Conditional Approvals" are debts that accrue interest in the form of yield loss.
Gate 0: Project Kickoff & Commercial Entry
Objective: Validate that the business case exists and the technical data is intelligible.
- Owner: Sales / Account Manager
Entry Criteria (Inputs):
- Golden Data Pack: Complete BOM, Gerbers, Assembly Drawings (See Ch 1.2).
- Commercial Coverage: NRE (Non-Recurring Engineering) PO received for EVT build.
- Target Pricing: Agreed Target Price vs. Estimated BOM Cost gap is < 10%.
Exit Criteria (Outputs):
- Project Schedule: Timeline locked with customer (T0 to SOP).
- Long Lead Items (LLI): Risk buy PO placed for components with lead time > project duration.
- Team Assignment: PM, Lead Engineer, and Buyer assigned.
Pro-Tip: Do not start engineering work without a PO or a signed Letter of Intent. "Goodwill" does not pay for engineering hours.
Gate 1: EVT (Engineering Validation Test)
Objective: "Does it work?" Prove the design intent and basic functionality.
Volume: Small (5 – 20 units).
Method: Soft tooling, manual assembly, quick-turn.
- Owner: Lead Engineer
Entry Criteria:
- Draft Bill of Materials (BOM) loaded in ERP.
- Primary components available.
Exit Criteria:
- Functional Pass: Units power on and perform primary functions.
- DFM 1.0 Report: "Showstoppers" identified (e.g., impossible solder joints, component collisions).
- BOM Scrub: Obsolete/High-risk parts identified.
Gate 2: DVT (Design Validation Test)
Objective: "Is it robust?" Finalize the design and materials. The product must meet all regulatory and reliability standards.
Volume: Medium (20 – 100 units).
Method: Hard tooling (molds) initiated, production-intent components.
- Owner: Quality Manager / Engineering
Entry Criteria:
- Design Freeze: No new features added after this point.
- Test Plan: Draft Functional Test (FCT) procedure defined.
- Tooling: Molds/Fixtures ordered.
Exit Criteria:
- Regulatory Pass: CE/FCC/UL certification samples pass.
- Reliability Pass: Thermal, Drop, and Vibration tests passed.
- DFM 2.0: All "Red" issues from EVT resolved.
- Test Fixture: Beta FCT fixture operational.
Decision Logic:
- If BOM changes > 20% → Then Repeat DVT. Do not proceed to PVT.
- If Hard Tooling requires modification → Then trigger Tooling Modification Approval (TMA).
Gate 3: PVT (Production Validation Test)
Objective: "Can we build it at scale?" Test the manufacturing line, not the product. Validate cycle time and yield.
Volume: Pre-production run (50 – 500 units).
Method: Production line, standard operators, final test fixtures.
- Owner: Operations Manager / Plant Director
Entry Criteria:
- Supply Chain: Material pipeline clear for Mass Production.
- Work Instructions: Standard Operating Procedures (SOPs) written and posted.
- Test Limit: Pass/Fail limits locked in the tester.
Exit Criteria:
- Yield Target: FPY (First Pass Yield) ≥ 95% (or agreed target).
- Cpk/Ppk: Critical dimensions demonstrate statistical control (Cpk ≥ 1.33).
- Cycle Time: Line moves at the quoted TAKT time.
- Golden Sample: Signed "Master Unit" stored in Quality Assurance cage.
Pro-Tip: If you fix a unit on the line during PVT without recording the root cause, you have failed PVT. PVT is about exposing the process failures, not hiding them.
Gate 4: SOP (Start of Production / Mass Production)
Objective: Release to volume manufacturing. Transfer ownership from Engineering to Operations.
- Owner: Operations Manager
Entry Criteria:
- PVT Sign-off: All critical open issues closed.
- Commercial Lock: Volume PO received; Pricing/Terms finalized.
- RMA Process: Defined and agreed upon.
Exit Criteria:
- Shipment of first commercial lot.
Final Checklist: The NPI Gatekeeper
Gate | Critical Control Point | Pass State | Owner |
G0 (Kickoff) | LLI Orders | POs placed for Silicon/LCDs/Connectors. | Sales |
G1 (EVT) | DFM Report | Critical design flaws highlighted to customer. | Engineering |
G2 (DVT) | Design Freeze | Customer signs off "No more changes." | Engineering |
G3 (PVT) | Yield Stability | 3 consecutive lots met yield target. | Ops |
G4 (SOP) | Test Limits | Test software version locked (Read-Only). | Quality |