8.13 First Article Inspection (AS9102)

First Article Inspection (FAI) validates that the manufacturing process is capable of producing a part that meets all engineering and design requirements.

8.13.1 The FAIR (First Article Inspection Report) Structure

  • Form 1 (Part Accountability): Identifies the part, revision, and organization. Summarizes the result (Pass/Fail).
  • Form 2 (Product Accountability): Lists all raw materials, special processes (e.g., plating, soldering), and functional tests. Requires mapping to specific Certificate of Conformance (CoC) numbers.
  • Form 3 (Characteristic Accountability): The detailed audit. Every dimension, note, and tolerance on the drawing is assigned a unique number ("Ballooning"). The inspector records the actual result against the required range for every single characteristic.

8.13.2 Trigger Events for FAI

A new FAI (or Delta FAI) is required when:

  1. New part introduction.
  2. Design change (Revision change).
  3. Change in manufacturing source, process, inspection method, or location.
  4. Lapse in production for two years.

Final Checklist

FAI Component

Requirement

Purpose

Form 1

Part Number & Revision

Identification

Form 2

Material Certs & Processes

Traceability of Inputs

Form 3

Ballooned Drawing Data

Verification of Dimensions

Delta FAI

Re-verify changed features

Change Management