8.7 Box Build & Mechanical Assembly (IPC-A-630)

IPC-A-630 covers the "Box Build"—the integration of PCBAs into chassis.

8.7.1 Hardware Installation

  • Torque Verification: All structural screws must be torqued to specified values.
    • Torque Striping: A line of "tamper paint" (Torque Seal) applied across the screw head and chassis. A broken line indicates loosening.
  • Thread Engagement: For screws into nuts, the screw must protrude at least 1.5 threads past the nut body.
  • Washers: Correct stack-up (Split washer -> Flat washer) is mandatory to prevent damage to the surface and ensure locking.

8.7.2 Chassis Cleanliness (FOD)

  • Foreign Object Debris (FOD): Any loose material (wire clippings, solder balls, washers) inside the enclosure is a critical defect.
  • Shake Test: A mandatory audible check ("The Rattle Test") for loose hardware before closing the box.

Final Checklist

Step

Action

Verification

Torque

Apply specified Nm

Click-wrench or Electric Driver

Marking

Torque Seal Paint

Visual (Unbroken line)

Gap Check

Enclosure Seams

Feeler Gauge (if spec'd)

FOD

Shake/Visual

No loose debris